EV analysis with wbs and activities

25 Views

Hi Guru's,

I have created a project definition intially with WBS elements structure.

Then i have planned the cost against WBS elements using ECP.

Then i have maintained the POC measurement method as Cost Prop.

after that i have run CNE1 and i am able to get the BCWS values against each WBS elements in CNE5.

Now the schenario i am trying with activities.

i just created a network and activities with work and duration (Cost is not planned on activities and it is planned on WBS elements)

After that i maintaining the POC measurement methods as Cost Prop (planned) and Work (Actual) for activites and i have not maintained any POC measurement method for WBS elements.

After doing this i have run the CNE1 and CNE5 but i am not getting BCWS values against activities.

Please help me guru's on this.