cancel
Showing results for 
Search instead for 
Did you mean: 

EV analysis with wbs and activities

Former Member
0 Kudos

Hi Guru's,

I have created a project definition intially with WBS elements structure.

Then i have planned the cost against WBS elements using ECP.

Then i have maintained the POC measurement method as Cost Prop.

after that i have run CNE1 and i am able to get the BCWS values against each WBS elements in CNE5.

Now the schenario i am trying with activities.

i just created a network and activities with work and duration (Cost is not planned on activities and it is planned on WBS elements)

After that i maintaining the POC measurement methods as Cost Prop (planned) and Work (Actual) for activites and i have not maintained any POC measurement method for WBS elements.

After doing this i have run the CNE1 and CNE5 but i am not getting BCWS values against activities.

Please help me guru's on this.

Regards,

rao

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi Guru's,

Please provide me your valuable suggestions on this issue.

Thanks & Regards,

rao

Former Member
0 Kudos

Hi guru's,

Please tell me one thing, if i plan costs at wbs level and maintaining activities for scheduling purpose only. In that case can i get EVA at activity level?

Please clarify me.

Regards,

rao.

Former Member
0 Kudos

Hi Bhadra,

              If you are not doing cost planning at activity level you won't get Earned Value at activity level.

EV =Base value(Cost or Budget)* POC

Base value will be zero if cost planning is not at activity level.

I hope it helps.

Former Member
0 Kudos

Hi B P Singh,

Thank you for your reply, i have tried the schenario for cost activity, even then i am not able to get EV.

pls help me.

Former Member
0 Kudos

Hi,

   Configure Progress analysis properly.If you use Cost as your EV Basis you will get Earned Values at activitiy level having cost.

Former Member
0 Kudos

Hi,

It is working fine for WBS element level, so i think there is no issue with configuration.

But i am not getting for activity.

I am maintaining Cost (annual) as EV basis and POC weight as Cost (annual).

Pls suggest me..

Former Member
0 Kudos

Please check this thread, it might help you

http://scn.sap.com/thread/1394997

Rabiee

Former Member
0 Kudos

Thank u for your reply Rabiee, i have checked that thread but is it not helpfull for my case.

Hi Guru's please help me....

Regards,

Bhadra rao