work center data

Former Member
0 Kudos

Sir,

  Our requirement is like this.

  Create a labor work center with all parameters and assign 9 people ( 3 ele+3 Mec+3 instr)

  Hr module is available.

 

I have created a work center

Basic Data: Work center cat -005, usage -009, standard value key-Sap1

 

Default Values: PM01

Capacity:  Capacity cat-002, setup formula SAP003,

 

Capacity:  Capacity cat-002, setup formula SAP006

Scheduling: Capacity: Capacity cat-002, setup formula SAP003, processing formula Sap001, workuit-Hr

Now, my requirement is how to assign Hr data, capacity planning, scheduling, capacity load, capacity leveling.

 

Please guide me with t code.

Rgds,

Saimeghana

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hello,

have you referred the link below for the steps ?

http://blog.sina.com.cn/s/blog_7c9243370100yjeh.html

Revert in case you need more details.

Regards,

Deepak

Former Member
0 Kudos

hi,

I have done up to some extent.

I have created shift sequence in op4a and unbale to assign in scheduling

intervals and shift area is grey out and also unabelt oeneter the data.

please guide me.

Former Member
0 Kudos

Hello,

I am unable to attach the config document.Hope you have done below steps in OP4A

In OP4A,

On the Change View “Grouping”: Overview screen choose New Entries and enter your profile name

Choose Enter.

Select your Shift Group and double-click Work break schedules.

On the Change View “Work break schedules”: Overview  screen choose New Entries and make the entries.

Double-click Shift definitions, choose New Entries and make the entries.

Now double-click Shift sequences, choose New Entries and make the entries.

Go back and save your entries.

Once you created/defined shift sequence in OP4A please follow below steps.

1.Define strategy profile (OPDB)

Strategy Profile

YQ___T001

Finite scheduling

X

Dispatch at earliest point in time

<No entry>

Dispatch at best time for setup

<No entry>

Date entry when dispatching

<No entry>

  1. Direction forwards

<No entry>

Change planning direction

X

Planning in non-work periods

<No entry>

Insert operation

<No entry>

Close gaps

<No entry>

PerSplit

<No entry>

Start search in plan direction

<No entry>

Always adhere to period split

<No entry>

  1. compl. In period split

<No entry>

Treatment of queue time

1 (After reduction level)

Reduction level

1

Overall capacity

<No entry>

Reschedule with prod. Version

X

  1. sequence

SAPSFCSS31 (Sort. order: lat.start/seq.no./prio)

Dispatch internal production

2 (Latest start date)

Initial setup state

<No entry>

Sort operations to be dispatched

X

Consider operation sequence in the order

X

Operation date check

<No entry>

Change production version on error

<No entry>

Midpoint scheduling

X

Setup time optimization

<No entry>

Cancel dispatching due to error

X

  1. Term.resched with prod version

<No entry>

Use operation floats

<No entry>

Use float bef. Prod.

<No entry>

Use float aft. Prod.

<No entry>

2.Define overall profile (OPD0)

Overall profile

YQPI_G001

Selection profile

SAPPI_S001

Control profile

SAPPI_C002

Time profile

SAPSFCZ002

Evaluation profile

SAP___A001

Strategy profile

YQ___T001

Period profile

SAP___P003

Planning tab. profile

SAPPI_L002

  1. pln.tab. (tab)

<No entry>

List profile

SAPSFCI001

With this you can completed capacity planning customization.

Regards,

Deepak

Former Member
0 Kudos

sir,

unable to create new capacity planner groupe.

any t code is there.

Former Member
0 Kudos

Hi,

Please follow the path

SPRO -> Production -> Capacity requirement planning -> Master data -> Capacity data -> Setup capacity planner

All the best

Regards,

Deepak