on 04-07-2012 7:12 AM
Sir,
Our requirement is like this.
Create a labor work center with all parameters and assign 9 people ( 3 ele+3 Mec+3 instr)
Hr module is available.
I have created a work center
Basic Data: Work center cat -005, usage -009, standard value key-Sap1
Default Values: PM01
Capacity: Capacity cat-002, setup formula SAP003,
Capacity: Capacity cat-002, setup formula SAP006
Scheduling: Capacity: Capacity cat-002, setup formula SAP003, processing formula Sap001, workuit-Hr
Now, my requirement is how to assign Hr data, capacity planning, scheduling, capacity load, capacity leveling.
Please guide me with t code.
Rgds,
Saimeghana
Hello,
have you referred the link below for the steps ?
http://blog.sina.com.cn/s/blog_7c9243370100yjeh.html
Revert in case you need more details.
Regards,
Deepak
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
I am unable to attach the config document.Hope you have done below steps in OP4A
In OP4A,
On the Change View “Grouping”: Overview screen choose New Entries and enter your profile name
Choose Enter.
Select your Shift Group and double-click Work break schedules.
On the Change View “Work break schedules”: Overview screen choose New Entries and make the entries.
Double-click Shift definitions, choose New Entries and make the entries.
Now double-click Shift sequences, choose New Entries and make the entries.
Go back and save your entries.
Once you created/defined shift sequence in OP4A please follow below steps.
1.Define strategy profile (OPDB)
Strategy Profile | YQ___T001 |
Finite scheduling | X |
Dispatch at earliest point in time | <No entry> |
Dispatch at best time for setup | <No entry> |
Date entry when dispatching | <No entry> |
| <No entry> |
Change planning direction | X |
Planning in non-work periods | <No entry> |
Insert operation | <No entry> |
Close gaps | <No entry> |
PerSplit | <No entry> |
Start search in plan direction | <No entry> |
Always adhere to period split | <No entry> |
| <No entry> |
Treatment of queue time | 1 (After reduction level) |
Reduction level | 1 |
Overall capacity | <No entry> |
Reschedule with prod. Version | X |
| SAPSFCSS31 (Sort. order: lat.start/seq.no./prio) |
Dispatch internal production | 2 (Latest start date) |
Initial setup state | <No entry> |
Sort operations to be dispatched | X |
Consider operation sequence in the order | X |
Operation date check | <No entry> |
Change production version on error | <No entry> |
Midpoint scheduling | X |
Setup time optimization | <No entry> |
Cancel dispatching due to error | X |
| <No entry> |
Use operation floats | <No entry> |
Use float bef. Prod. | <No entry> |
Use float aft. Prod. | <No entry> |
2.Define overall profile (OPD0)
Overall profile | YQPI_G001 |
Selection profile | SAPPI_S001 |
Control profile | SAPPI_C002 |
Time profile | SAPSFCZ002 |
Evaluation profile | SAP___A001 |
Strategy profile | YQ___T001 |
Period profile | SAP___P003 |
Planning tab. profile | SAPPI_L002 |
| <No entry> |
List profile | SAPSFCI001 |
With this you can completed capacity planning customization.
Regards,
Deepak
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.