Hi All,

Please help me with this, I need to make GI (261 MT) to production order from transfer order confirmation, is there any batch job  program available to do that or do i need any configuration set up to do this or is there any customization?

I could able to generate TR from production order release with 319 movement type and later converting to TO and confirming it, when it confirms the stock is showing in destination storage bin but at the same time i need to happen goods issue to production order...

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Check the setting at below config,

Warehouse Management --- Interfaces -- Inventory Management --Shipping  ---Define Shipping Control at the Movement Type Level.

Reward if helpful.

Regards

Sumanth

Former Member
0 Kudos

but this option is not working for production order, this works only for deliveries.

Former Member
0 Kudos

Hi,

Then probably an exit should be implemented after the TO is confirmed, if it is a dynamic bin. Identify the Bin number as production order and PGI it.