I have a problem regarding maintenance plan scheduling.

When I am scheduling a maintenance plan, ther is a error in the log which says:

error: Date 18.05.2013 is after the factory calender ZK, maintenance plan 862.

Please revert back for the solution.

Regards,

asheesh

Accepted Solutions (0)

Answers (3)

Answers (3)

former_member374929
Active Participant
0 Kudos

hey thanx both of u.....

Former Member
0 Kudos

Hello Asheesh,

Go to Tcode SCAL,Select Factory Calender,click on change icon,Double click on your factory calender ZK and extended the filed "Valid to year" to 2013.

Regards,

Deepak

shailendradupadhyay
Contributor
0 Kudos

Hi

Please check in SCAL your calendar (ZK) validity extended upto 2013  or not.

shail