on 03-30-2012 6:50 AM
Hello Experts,
Its a construction industry and i need to bill the customer based on the completion of work.Ther is no material involved in it.Hw can bill the customer without material.I have tried using text item but it does not allow pricing.And from PS point of view,we have only 1 WBS element and we are not creating any network activity.The reason for not creating network coz company cannot determine the actual work.we are covering only the total revenue.
I need to bill the customer say for example
Project - ABC - Revenue - 5000 USD
Say Roofing is the activity which i need to bill for the amount 1000 USD which will break in the below phase.Roofing is not defined in PS.So based on completion of work on % i wil bill as mentioned below.
Phase 1 - 10% - 100 USD - 1st billing
Phase 2 - 30% - 300 USD - 2nd billing
Phase 3 - 70% - 700 USD - 3rd billing
Integration point of view i wil take care.
Can you all suggest some solution.
Thanks
Shri..
Explore option of Billing Plan (Milestone Biling) and milestones will come form project.
For this you might need a material (service) and you may use standard Item Cat TAO.
You can refer following Links from SAP help for understanding/reference:
In case of any doubt or further information, do revert back with your concerns.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
7 | |
7 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.