Former Member
0 Kudos

Hello Experts,

Its a construction industry and i need to bill the customer based on the completion of work.Ther is no material involved in it.Hw can bill the customer without material.I have tried using text item but it does not allow pricing.And from PS point of view,we have only 1 WBS element and we are not creating any network activity.The reason for not creating network coz company cannot determine the actual work.we are covering only the total revenue.

I need to bill the customer say for example

Project - ABC - Revenue - 5000 USD

Say Roofing is the activity which i need to bill for the amount 1000 USD which will break in the below phase.Roofing is not defined in PS.So based on completion of work on % i wil bill as mentioned below.

Phase 1 - 10% - 100 USD - 1st billing

Phase 2 - 30% - 300 USD - 2nd billing

Phase 3 - 70% - 700 USD - 3rd billing

Integration point of view i wil take care.

Can you all suggest some solution.

Thanks

Shri..

Accepted Solutions (0)

Answers (1)

Answers (1)

jpfriends079
Active Contributor
0 Kudos

Explore option of Billing Plan (Milestone Biling) and milestones will come form project.
For this you might need a material (service) and you may use standard Item Cat TAO.

You can refer following Links from SAP help for understanding/reference:

In case of any doubt or further information, do revert back with your concerns.

Former Member
0 Kudos

Hi JP,

Thanks for your reply,when i enter WBS element to my material its not reflecting in invoice line item.

Can u suggest.

Thanks

Shri..

jpfriends079
Active Contributor
0 Kudos

If you have enterred WBS in your sales order - item data Account assignment tab, then you will be able to see W your WBS in Invoice - Item Data - Item Detail Tab - Account assignment section. For that you may have to scroll down a bit in Item Detail tab. Refer following screenshot: