cancel
Showing results for 
Search instead for 
Did you mean: 

urgen change: Task list is not created

Former Member
0 Kudos

Hello experts!

I created Urgen change.

My error: No maintenance cycle is open for the current system

Text log

-------------

General Note

28.03.2012   17:51:39   Дмитрий Владиславович Захаренков /

Task list  created in SAP Change Manager

-------------

Why is not number of Task List  displayed in Task log? How to solve this problem?

Accepted Solutions (0)

Answers (5)

Answers (5)

Former Member
0 Kudos

Hi Dmitry,

This is due to authorization issue for Developer role in solman 7.1.

Try with admin user and recheck the transcation.

This issue will disappeared.

Rg,

Karthik

Former Member
0 Kudos

I appropriated SAP_ALL to the my user. The error remained

Former Member
0 Kudos

Hi Dmitry,

what is the status of your maintenance cycle: "created" or "in development.."?

Could you check it, please?

Best regards

Horst

Former Member
0 Kudos

in development...

Former Member
Former Member
0 Kudos
17. Error "No maintenance cycle is opened for the current system"

When creating a normal correction or urgent correction (or setting it from "Created" to "In development"), the customer receives error "No maintenance cycle is opened for current system." (SOCM_ACTION_LOG011).

Possible reasons are:

- The IBase is wrong: The IBase/component must represent the production system in the project landscape.

+IBase component is represent the production system (SW2)

- Lack of authorizations: Assign role "SAP_SOCM_ADMIN" or "SAP_CM_ADMINISTRATOR_COMP" (or equivalent) to the user who would like to approve the change request.

+ I have many roles and SAP_ALL

- Project is locked in table /TMWFLOW/PROJMAP: If an error is detected during the processing, then the project might be locked in this table. The customer can unlock it by pressing the refresh button under tab "System Landscape" -> "Change Requests". If there are other error messages shown during the refresh process, the customer must fix those errors beforehand.

+ Status of Project in table /TMWFLOW/PROJMAP is ACTIVE

P.S. The 'Check' button under tab 'Change Requests' (the same as transaction /TMWFLOW/CHARMCHK) will only do the checking. On the other hand, the 'Refresh' button will do the checking and update the relevant database entries.

+ I checked it. I Created the new Maintance project. The error remains.

Former Member
0 Kudos

Hi Dmitry,

did you check the status of your maintenance cycle? The maintenance cycle should be in phase 'in development'.

best regards

Horst

Vivek_Hegde
Active Contributor
0 Kudos

Hi,

When creating the Urgent Change Correction, make sure that in the 'IBase / Compnent' section you refer to the actual Production system, and not to your Development system.
Also make sure you have assigned auth object S_PROJ_GEN to the user.

Regards
Vivek

Former Member
0 Kudos

1. IBase / Compnent = Product system

2. I have assigned auth object S_PROJ_GEN to the my user

Former Member
0 Kudos

Hi,

Pls check the Authorizations of the User which is closing the previous task list before opening a new one.

Second, go to the IMG project and check if CTS check box is ticked or not , if not correct that first.

It happens that when a user without authorizations closes off the maintenance cycle the IMG project goes off on CTS..

Regards,

KK.

Former Member
0 Kudos

Hi,

Can you go to the tasklist in SMCA or SOLAR_PROJECT_ADMIN and unlock all the tasks linked to the cycle and try?

Thanks,

Jagadish.