source inspection

Former Member
0 Kudos

Dear experts,

I have created a material & created a quality info record for the same with required settings for source inspection.

I have maintained a control key in QM view of material master which specifies that no GR is allowed if  source inspection is rejected & creation of no new inspection lot.

Now when I created a PO and execute the T Code-QI07 I am getting message as-No source inspections are required-message-QB151.

Can anybody help me to resolve this issue.

Your help is highly appriciated.

Vivek

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Have you activated he inspection type for source inspection what ever you have maintained in quality info record?

Regards,

Smruti

Former Member
0 Kudos

Yes. it is mentioned in QIR & in material master also

Former Member
0 Kudos

Hi please check in PO under delivery tab what is maintained for stock type and qa control key. It should be quality inspection and the key you have maintained in material master.

Regards,

Smruti

Former Member
0 Kudos

The stock type is QA & the control key is also correct in delivery tab

Former Member
0 Kudos

then what is the delivery date you have mentioned is it some future date? ie. the delivery date is beyong the lead time you have defined in QI info.

Former Member
0 Kudos

No it was not a future date but a prior date before the release date in PO.

Now I put the exact date what is mentioned in PO & then execute. Now I got the line item of PO. But now when I click on create inspection lot button, nothing is happenning and no inspection lot is getting created

Former Member
0 Kudos

Source inspection lot gets triggered successfully. and when it was rejected, sytsem did not allowed me to post GR for the said PO number as per my requirement.

Thank u for your valuable & prompt replies

Answers (2)

Answers (2)

Former Member
0 Kudos

Make sure that Qm proc tick is active and control key selected is either of "quality assurence aggre"  or/and "relase require " .

Former Member
0 Kudos

Hi Vivek,

uncheck source inspection No GR.

tHANKS

Former Member
0 Kudos

1.Maintain 01 inspection type along with 0130 in QM view inspection setup.

2.Maintain 0130 inspection type "for Soruce inspection" in Quality Info record.