on 03-19-2012 8:01 AM
Hello All,
I am getting an error when settling the WBS to AUC (Investment project). I have booked cost via
activity confirmation (rate defined in KP26 and cost element ZZZ).
When defining activity type (to be used in KP26) i can assign only secondary cost element, now when i run
settlement run i get an error message "G/L account ZZZ" does not exist, but i cannot create G/L account
corresponding to a Secondary cost element??
Any pointers to address this will be really helpful
Regards,
Jatinder
hi
check whether you have created the XXX as cost element also and also mentioned in the cost element group for settlement