Hi

I have an issue in the planned order that are generated for the level 1of the configurable materials, This is also a configurable materials and i have written a procedure to cope the value of the characteristics from the parent to this level. It works fine in CU50 , i could see the components. But when i crate a SO , the planned order that is generated for this second level configuirable material , does not have any components.

i have written code like this in the procedure

$self.Z_PC_UPS_BATTERY = $parent.Z_PC_UPS_BATTERY if specified $parent.Z_PC_UPS_BATTERY , $self.Z_PC_UPS_INVERTER = $parent.Z_PC_UPS_INVERTER if specified $parent.Z_PC_UPS_INVERTER.

any suggestion to solve this issue.

Prasanna

Accepted Solutions (0)

Answers (2)

Answers (2)

Ritz
Active Contributor
0 Kudos

Prasanna,

If you are able to simulate it using CU50 it should work fine with SO too, please check your configuration profile for second level configurable material , specialy the settings for plan order creation and BOM explosion.

Check and revert back.

Ritesh

Former Member
0 Kudos

Hi

MRP 3 view with strategy was missing , after maintaining that i could get the components for the second level.

former_member228481
Contributor
0 Kudos

Would you specify the BOM levels, And which char is assigned at which level?

Br