we have a delta monthly load to a cube from six source systems( All R3) schedulled by a

infopackage group, Now the problem is .... except one infopackage all the other five the

delta load has failed 4 months back , update type is only PSA ,update subsequently in data target

now i have to reload the cube from the 5 Source systems with all the data (delta) for the last 4 months ,

i have planned to delete the failed request from the PSA ,

Initialize delta without data transfer

and schedule the infopackage ..

I would like to know ............

is there a better way of doing this?

is there anything mandary to perform before this?

Thanks form any of your sugesstions,

SS

Add a comment
10|10000 characters needed characters exceeded

Related questions

4 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on May 25, 2005 at 05:30 PM

    Arun is right. You can reload from the PSA package by package. If you reinit you will never know what the problem was. Before you start the reload you will have to delete the failed loads. You will have to do this carefully because the valid packages might also get deleted. In this case you will have to reload some of the valid packages too.

    Hope it works well for you.

    Jita

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on May 25, 2005 at 11:29 AM

    Hi Sathya,

    I dont find any reason of doing Init again even without data transfer.

    Can you please tell what is the reason of failures any error message.

    Otherwise try to reconstruct the delta.

    Hope this helps.

    Regards,

    Ashish

    (Reward with points if the solution helps you)

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on May 25, 2005 at 11:42 AM

    going by what you have sent , you have failed delta which means that the init was successful. Go into the PSA - check what the error was and load the delta from PSA. That way you :

    1. Do not have to init again

    2. You will not have the problem of delta pointers in R/3 which would be current and you would want delta for an older date.

    This mightbe actually the best way but then again it depends on how many requests you have to upload manually.

    Arun

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on May 26, 2005 at 04:08 PM

    Thanks for all your valid sugesstions,

    I have sucessfully done with it ,

    Best Regards & Thanks ,

    SS

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.