Hello Expert,
Please let me know or share some document on CIF issues while transferring the PDS and TLANE.
What are the things/point need to check if PDS and Tlane not transferred to APO.
Thanks,
Jeet
Hi Jeet,
This query is a bit broad, but my first tip would be checking ECC outbound/APO inbound queues and, if find anything stuck, analyse it further.
I assume you are ciffing the mentioned data via an Integration Model. Are you facing any errors when activating some of the integration models, at all?
Are you able to see the PDS in APO, tcode //curto_simu?
Please refer to the following KBA, I believe it has valuable information for you, even if your PDS type is not subcontracting:
1753769 - How to create a Subcontracting PDS
Thanks & regards,
Pablo Moraes
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
For PDS, please check following-
1. BOM and production version are created properly in ECC
2. All materials and locations are in APO already
3. There is no older version of PDS available in APO, if yes delete the same and try to send the PDS again to APO. This helps sometimes.
For TLANE,
1. Check if Source list/PIR/SPKs are created whichever is applicable for the material.
2.Check if both the location are present in APO
3. If creating product specific MOT, make sure material is extended to both locations in both ECC and APO.
Regards,
MB
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.