i want check during goods receipt subcontracting po input quantity and out put quantity.if it is there any difference between Po and GR. i want to GR level it self please help me

Regards:

Suresh balli

10 |10000 characters needed characters left characters exceeded

Hi,

Your question is unclear,please provide some screenshot to explain.

Regards,

Avik

0
* Please Login or Register to Answer, Follow or Comment.

2 Answers

avatar image
Former Member Jul 29, 2017 at 09:09 AM
0

Hello,

is it possible to put tolerance limit at the time of goods receipt.

Suresh

Share
10 |10000 characters needed characters left characters exceeded
Jürgen L
Jul 29, 2017 at 12:04 PM
0

"is it possible to put tolerance limit at the time of goods receipt."

Why should a receiver himself enter a tolerance which would restrict him from doing what he actually wants to do.

Tolerances are usually set by a buyer to have some control over the activities by the receiver.

"i want check during goods receipt subcontracting po input quantity and out put quantity"

A receipt to a subcontract PO is actually automatically backflushing the components based on the bill of material from the PO. The receiver usually only enters the quantity that had arrived. Checking a tolerance between input and output would mean that the bill of material is incorrect.

You may want to explain your needs with an example and also what problems you with your current setup actually have