Error in Easy Cost Plannning

Dear Experts,

Im doing activity Cost plannnig through Easy cost plannnig.I need to do activity cost Planning without cost element.But As of my knowledge it is not possible ..Is there any possiblility to do like that .Can i use WBS Element Instead of Cost element..??...

Please Suggest...

By

Suma

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Mar 05, 2012 at 08:49 AM

    Hi Suma,

    No, It is not possible, Activity cost plan is based in cost element,

    Regards,

    Sara

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi,

      Whenever you have any doubts on use/definition use F1 and try to get infor from SAP itself. In this case the Cost element is Required if we use the variant in ECP as per SAP. Pl see the info which am copying from F1 help.

      Usage Indicator for Cost Element in Unit Costing

      This setting controls whether the entry of the cost element is mandatory (Required), optional (Allowed) or whether you are not allowed to make an entry (Forbidden) for the cost estimate. In Easy Cost Planning this setting is always overridden by Required.

      Reg/ Tony

  • avatar image
    Former Member
    Mar 05, 2012 at 10:58 AM

    Sorry, I can't help you, I am not an expert related to costing variants ( I have always used the PS06), The only I know is there are 2 ways to plan costs in PS ( overall --> CJ40) and the other ones are based in cost element because are registered in cost element tables.