on 03-02-2012 7:51 AM
Dear All,
I have created a customer project and corresponding Sales order with account assignment as WBS element.
So i am expecting that in output of report S_ALR_87013531 i should get both cost and revenue figures, but in output if the report revenue is not flowing from Sales order?
Please note that FROM SALES ORDER indicator is ticked and Rev Ele From Billing is maintained in Planning profile being used.
I have not created billing plan for WBS; because i am driving Billing from sales order.
What else could be the possible reason for revenue not flowing in WBS?
Regards,
Jatinder
Are you gettng the revenue in CN41 report?
Thanks and Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
The cost element for revenue must have category 11 and it should be included in element group assigned in planning profile. Make sure you create new project and SO after changes.
Also in SO check if correct G/L account is determined, you can do that by going into Environment>Analysis>Account Determination in VA0
Regards
Shrikant
Edited by: Shrikant Rakate on Mar 2, 2012 3:44 PM
User | Count |
---|---|
102 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.