MRP Groups

36 Views

Hi

I have created MRP group with following control parameters

Planning horizon 20 days

Creation indicator -- PR in opening period

Opening period in material master 10 days

I have requirement on 3.04. 2012 andi put planning date in Md01 6.03.2012 ( 3.04. 2012 --- 20 days ) then MRP does not create any procurement proposal.

Stock is zero.

Planning horizon for plant is 1 day.