on 02-28-2012 6:14 AM
Hi Friends,
We are trying to release a billing document to accounting. However, we are getting an error of "No std cost estimate could be found for material 616091" The long text shows that "No valid material cost estimate exists in plant PH98 for material 616091"
However, if we check the billing document, the plant which is maintained is PH81 and not PH98 (which is admin plant).
Please let us know how do we resolve this error.
Rgds,
Kunal
Hi,
Kindly check the below link
http://forums.sdn.sap.com/message.jspa?messageID=7198049
Regards
Gautham.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Kunal-
Do you have COPA implemented in your system? If so, please look at this forum which has some wonderful pointers.
http://forums.sdn.sap.com/thread.jspa?messageID=10174869#10174869
Shail
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Mate,
Please check the material in MM03 - Plant is either PH98 or PH81. System will not shows an error which is not an error.
After that, just ask you CO Consultant that whether the Costing has been released for thos material or not.
If not,
CK11N - Run costing with right Costing Variant
CK24 - Mark and release
Take the help of CO Consultant
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
88 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.