Hi,

I've assigned equipment PRT to Network activity. Now i want to record the usage time for equipment. How shall i do the confirmation for this equipments. Can anyone put some light on this please...

Thanks

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Create an activity type for PRT equipment. Create an work center for that PRT equipment (either for single machine or machine group, based on your requirement).

Maintain activity pricing in KP26.