cancel
Showing results for 
Search instead for 
Did you mean: 

MRP does not consider the transits

Former Member
0 Kudos

Hello Friends

user states:

We have a problem with the releases to suppliers, the MRP do not consider the transits by the time the MRP runs so if there is material in transit the supplier continues seeing as if there was backlog.

Your help will be appreciated.

Regards.

Edited by: Jürgen L. on Feb 27, 2012 11:13 PM

subject changed

Accepted Solutions (0)

Answers (1)

Answers (1)

tejyadav
Active Contributor
0 Kudos

MRP do not consider the transits by the time the MRP runs

Use OPPQ or Goto SPRO -> MM -> CBP -> Plant parameters -> Carry Out Overall Maintenance of Plant Parameters ->Click Maintain for your Plant & Select Available Stocks mark the Stock in transfer over there for your requirement, Check