on 02-25-2012 4:02 AM
Hi,
I want that system should automatically populate Basis end date in the WBS element based on the end date of last activity assigned to this WBS,
Scheduling Scenario i am using is 2 - Top Down Scenario, so system is taking project start date as date on whihc i create the project, but end date remains blank? how can we setup the system so that this end date is also automatically populated.
Thanks in advance.
Warm Regards,
Jatinder
Hi,
Please check the Scheduling Type you are using i.e Forward or Backward.
In your case you are entering start date , hence you should you use Forward.
At time of scheduling system will determine the End date.
Now this poulate at WBS you need check folowing things.
1. Adjust Basic Dates Indicator Checked.
2. Use Strict bottom up if it permits.
Later perform Edit > Extrapolate dates in PPB
Thanks,
Nitin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.