Hi SRM Experts,

Good morning.

In SRM 7.0, We have huge number of custom Badi's for SC, PO and Inv. Those are working fine in production system.

We are planning for upgrade and we made a system copy of all the SRM 7.0 objects and did the Upgrade of SRM 7.0 EPH1 in a new development system.

After the upgrade, SC custom workflows are not working. But I try to change with the SAP standard Badi's in the configuration and those are working fine. It's not working only for custom process level Badi's.

While we debug the custom process level workflow Badi's, we found that the SAP standard program not populating any value in MO_CURRENT_LEVEL and MO_FIRST_LEVEL in /SAPSRM/CL_WF_PROC and those entries are blank.

We're facing this issue for almost 2 weeks.

Please give your thoughts.

Thanks in Advance,

Best Regards,

Selvamuithu Natarajan