Dear All,

We are using Characteristic Dependent Planning (CDP) to plan configurable materials.

The requirement is to control the behaviour of Dynamic Pegging of a dependent requirement to receipt. We are using MTS strategy.

The BOM is P2 -


> P1.

Now P1 and P2 have characteristics called Length, WIdth, Grade,etc. The normal CDP based pegging considers all the characteristics and tries to match them. However we wish to peg only based on Grade and WIdth (the characteristic Length is not pegging relevant but only for information). We cannot make Length as APO non relevant.

We have already modified the heuristic such that it doesnt consider length in netting off.