Skip to Content

Error while Creating Network Activity

Dear Team Members,

I am getting an error while creating a new activity in Project Structure. The Project Network is already created and released. While saving new network activity under same WBS or other WBS, I am getting an error saying "Express document-Update document terminated-received from other".

While analyzing dump I observed that its giving dump since an entry already exists in COBRA(SettlementRule) table. Settlement rule generated automatically for WBS where network activity is attached. Since there are already activities are present in the network and released, settlement rule is generated for these activities. Now, when I am creating another activity under the same, on saving I am receiving this error.( Attached screenshot)

Now, when I have checked the same thing for other projects it's not happening but, it's happening for specific projects only. wherein there is no difference between two projects.

Any clues why it's happening.

Regards

Atul Rajmane

capture-1.png (23.2 kB)
capture-2.png (28.1 kB)
capture-3.png (107.6 kB)
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Dec 27, 2016 at 09:22 AM

    please check with abap team with this trace.

    Add comment
    10|10000 characters needed characters exceeded

  • Jan 03, 2017 at 10:49 AM

    Implemented SAP Note correction 2381326 for Dump.

    Add comment
    10|10000 characters needed characters exceeded