Inspection Lot Status UD ICCO SPCO ORRQ

Former Member
0 Kudos

Hello Experts,

Please share your thoughts on the System Status "UD ICCO SPCO ORRQ". Not sure on why the Lot getting the status ORRQ "Order record required"

What is the Condition in which the system triggers this Status? how to complete the inspection processing once we get this status? Is it a Particular Configuration setting that expects a Process Order Record?

Appreciate your quick response.

Regards

Raja

Edited by: rajatamil on Feb 22, 2012 5:19 PM

Accepted Solutions (1)

Accepted Solutions (1)

former_member42743
Active Contributor
0 Kudos

The ORRQ is related to the production side. Until the order record is created, you will not be able to archive off the inspection lot. The order record is required because it was required by the production order that caused the inspection lot to be created. I.E. your production folks still have some work to be done.

FF

Former Member
0 Kudos

Hello

Can you please eloborate what setting in Production Order / Process Order triggers this requirement for ORRQ status in Inspection Lot?

Regards

Raja

former_member42743
Active Contributor

Answers (1)

Answers (1)

former_member385375
Contributor
0 Kudos

UD- Usage decision made

ICCO- All inspection completed

RREC- Result confirmed

SPCO-Stock posting completed

I think afetr UD there is nothing to be done from QA side. Will you tell about the detail process, I mean what inspection lot origin you have used etc