Skip to Content
avatar image
Former Member

APO Capacity report /sapapo/cdps_rept is incorrect.

The Resource capacity consumption report /SAPAPO/CDPS_REPT does not match the data in the capacity planning book for monthly data view and also for weekly data view.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Jan 02, 2017 at 09:09 PM

    Hi Srivatsan,

    PP/DS and SNP do not follow the exact same logic, so there may be some differences in a few cases.

    Are there SNP planned orders scheduled during a downtime in the Resource? If yes, this can cause the difference in the Bucket Capacity Consumption, as in PP/DS the utilization rate is usually the integral of the capacity consumption during working times of the Resource (because orders in PP/DS cannot be scheduled during a downtime).

    Regards,
    Tiago

    Add comment
    10|10000 characters needed characters exceeded