Making vendor down payment at PO header level and not item level

former_member221515
Active Contributor
0 Kudos

Hi

I am making downpayment to vendor. I am using new functionality in EHP 4 for making downpayment through purchase order. When I run ME2DP for making downpayment, it asks for PO item number also.

But my requirement is to pay downpayment at PO header level and not PO item level.

Please let me know how can I do payment at PO header level.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Down Payments will be shown at header level only But when we are entering those you need to Enter the PO Number along with Item Number also.

Regards

Sridhar

Former Member
0 Kudos

Dear All,

I am also facing the same problem. Though Advance is maintained in PO Header Level when we are trying to create  DP Request / DP system is asking line item mandatory. Suppose i have 2 line items  and maintain all the DP amount in first line item. I am making service entry for 2nd line item and bill for the second line item. Then in this case, the Down Payment clearing tab doesn't appear in MIRO. That means I am unable to adjust the advance for the line item though I have to adjust it.

Problem is that there are more than 300 lines items in PO/WO. Hence it becomes difficult to maintain advance for each line or the user is forced to maintain certain amount in line item..

Please help ..Its urgent

Regards,

Ganesh

Answers (3)

Answers (3)

former_member425270
Discoverer
0 Kudos

Anyone got any resolution to this? We are currently faced with the same problem and looking for a solution.

sattaiah_gundu1
Participant
0 Kudos

Hi,

Is this issue resolved? If yes could you please explain.

Warm Regards

Sattaiah Gundu

former_member220489
Active Contributor
0 Kudos

Down Payments will be shown at header level only, but when we are entering them, you need to enter the PO no along with item number also.

Since when we settle this down payment during payment, system will treat this DP is for the full PO only.

former_member221515
Active Contributor
0 Kudos

There are more than 50 items in PO with different values. Like

Item 1: Rs.10000

Item 2: Rs.13200

Item 3: Rs. 9660

and so on...

I want give Rs.15000 as advance. So i will have to calculate manually the amount of advance that need to allocate to each item. Is my understanding correct?.

Or system will automatically divide advance amount at each item level?

Edited by: Deepak Agrawal on Feb 22, 2012 1:39 PM

former_member220489
Active Contributor
0 Kudos

Down Payments are always at header level only.

But when you make down payments, you just need to enter the first line item number atleast next to the PO no filed during posting.

No allocation to each item at all.

former_member221515
Active Contributor
0 Kudos

It means, all my advance will populate in one item only.