Hello PS Experts

Is it possible to change the value of the field in activity e.g. normal duration by formulation maiintained locally on standard network-activity through procedure dependancy when project or concerned network and activity is in Released status?

I am observing that when activity is in CRTD status, I can bring the change in Normal duration value by changing appropriate characteristics values ( base transaction is CJ20N). But similar change is not possible when NWK-Activity is in Rel status? Is there any solution available to this problem?

Your urgent feedback on this issue is highly appriciated...