Hi Guys,
I am trying to plan costs in CJ40 wbs wise it is not updating to the main WBS. As i have maintained the Planning profile as Bottom-up Planning and in Budget profile i have selected both Overall & Total values.
When i am trying to total up it is not updating the total values to the main WBS, can some one give me an idea.
Earliest replies are highly appreciated.
Regards
Hemadri