Dear Experts,
I have maintained Fixed and Variable price in KP26 for an activity against one cost center.
The secondery cost elements for such activities I have maintained in OKTZ.
When I am doing Standard cost estimate it showing some difference in cost for the activity.
If I maintained only variable price, the estimate for the activity cost is correctly calculating.
If I maintained only Fixed price, the estimate for the activity cost is differ as compared to kp26 calculation.
If I maintained both the prices say Fixed and vairable price, the estimate for the activity cost is differ as compared to kp26 calculation same as fixed cost case.
I am expecting the following:
1, What is the logic behind fixed cost calculation.
2,Please suggest which cost fixed / variable is suggestable to maintain in kp26 . Here Our activity is machine.
Jyoshna