Hi All,
For PO version magmt. the following are the two cases..
1.) PO created, saved and released. Now after release i want to change the PO then new version should be created(without taking the print of PO)
How do i go about it.
2.) PO created, saved, released and ME9F. Now again i want to change the PO then new version should be created.
How do i go about it.
Pls help.
Thanks in advance.
Regards.
Hi,
System will create a new version only if the document is outputted.
Please check the below link for more info
[http://help.sap.com/saphelp_erp60_sp/helpdata/en/8a/60b43bb7492147e10000000a114084/content.htm]
Thanks & Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Its SAP standard behavior no new version without Output, try this workaround if it helps you,
Maintain message MEDCM027 (No new version created because a message has not yet been transmitted) as error & try,
Use T-code OLME -> Environment data -> Define attributes of system messages -> System messages.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
1.) PO created, saved and released. Now after release i want to change the PO then new version should be created(without taking the print of PO)
How do i go about it.
as mentioned by someone above - without having NEU green (i.e. message output complete - which will create version 0) you can't have another version (for changed PO)
2.) PO created, saved, released and ME9F. Now again i want to change the PO then new version should be created.
How do i go about it.
this is how standard SAP works with purchasing doc version management if relevant configuartions are done correctly in SPRO
yogesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
The answer to Question 2 in Note 664928 should answer this for you. What you are seeing is standard behaviour.
664928 FAQ: Version management
2. Question:
You change a purchasing document (request for quotation, purchase order,
contract scheduling agreement). Why does the system not generate a new
version?
Answer:
The system always creates a new version when the purchasing document
reaches a final processing state. These are the following processing
states:
- Active if no release is used
- Release completed if the release is used.
...
Regards,
Purnima
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.