on 02-14-2012 11:00 AM
Hallo,
We are on ECC 6.0 EHP5 SRM 5.0 EHP1 SAPKIBKT18
We have the following problem. When we want to confirm in SRM PO's which are booked on an Asset the following error occurs:
System status INCM is active (Confirmation 187950)
Transaction CO Through-postings from FI has been locked (Item 1)
We don't have the error when confirming a Purchase order created on a Cost Center or WBS Element and it only occurs in our productive system. We have checked the following
CO through posting open and/or locked and they are ok (Confirmation on Cost Center and WBS Element works so it should be)
The master data of the PO. Can't see anything there
Master data of the Assets
Autoriation of users who are logged in and the RFC users
We cannot seem to find the problem maybe some of you have encountered this ?
Thanks!
hi
check in OKP1.
and unlock for the FI Postings.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Stork
Can you check this path - Financial Accounting(NEW)-Asset accounting -Asset data transfer - Parameters for data transfer- Dataspecifications -
1.Select specify transfer date/last clossed fiscal year -
were you maintained Take over date
2.Specify last period posted in Prv.system
were you maintained your company code against of period in which dep.area posted
Regards
Shankar