on 02-13-2012 10:30 AM
Dear SAP gurus,
I have read that when we use classic scenario, procurement for direct materials actually using extended classic. But as per SRM 7 EHP 2 the true classic PO (leading PO in ECC) now possible.
I just want to confirm is there any restriction in the backend side? E.g what is the minimum version of ECC that we should use for this scenario?
One more thing, I assume that in classic scenario we can have SC or external requirement goes to Sourcing Cockpit, and then we can proceed to create RFx or Auction from here rite? From here, I assume we can create PO from the response and it will create directly in ECC. is this correct?
Best regards,
John
Hi John,
R/3 4.7 is the minimum version supported with SRM 7.0 EhP2.
You can use direct material scenario from R/3 4.7.
Processes described by you should work.
Best regards,
Ramki
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ramki,
thanks for the confirmation. one more thing, can we setup different po type in classic scenario when we're creating po from rfx response? as i understand we can only setup one number range for po backend in srm config, so what should i do if i want to specify that user can chose the po type that they want to create in backend as a follow on from rfx response?
best regards,
john
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.