on 02-10-2012 1:02 PM
Refurbishment
Material & Equipment serial no assigned
Case 1.
1. Equipment Dismantled ( Ie02- structure tab)
2. In IE4n
Movement type 501 & also tried 262 & I got this
Dismantling not possible: No superior equipment exists for equipment 10006397
Message no. IEN108
Case 2
1. Equipment installed in FL
2. In IE4n u2013 entered material, equipment & serial eneterd
Movement type 501 & pressed check button
Message/errors
a. Structured gap can be created at FL
b. Simulated dismantled of equipment form FL failed
Case 3
1. Equipment installed in FL
2. In IE4n u2013 entered material, equipment & serial
3. Order created pm01
Movement type 262
Message: System status CLSD is active
Checked in the forum and unable to resolve
Please guide me
It looks like the order is closed (system-status CLSD)...
PeteA
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Sirs,
1. I have created split valuation for material (c1,c2,c3) -ok
2. stock posted & checked in MMBE ( stock is visible)-ok
3. equipment created with serial no and material no (split valued material) and checked in -sert-ok- and installed in FL.
4. now in ie4n,
I tried to dismantle the equipment
movement type-501
entered material no and equipment no and checked
errors
at least one error occurred during attempted pm/mm posting
message no Message no. IEN131
in the application log
Enter valuation type
Message no. M7347
Diagnosis
The material is subject to split valuation, but you have not chosen a valuation type.
System Response
The system can only post the document if you have assigned the quantity to a valuation type.
Procedure
Enter a valuation type.
If you do not know the valuation type, use the possible entries function to view a list of the existing valuation types for the material.
Please advise me.
Rgds,
Vsrao
If your mateial has split valuation for example
Defective = £5 as scrap value
Fit for purpose = £100 not new but fit for purpose.
New = £ 175 new item never been used
when asked you need to specify which valuation the material is to go into. If you do not know and an inspection is required then it should be returned as Defective and after inspection can be transfered to fit for purpose or sent for repair.
Jim
User | Count |
---|---|
100 | |
11 | |
10 | |
6 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.