Dear Experts,

i have created holiday calendar (HD), personal subarea grouping 01, daily work schedule as NORD, defined period work schedule as GENL(general Shift), i have taken 2(salaried staff) as work schedule grouping, work schedule rule as DWSR.

when i am doing generate work schedules manually i am giving

ESG: 2

Hoilday caleder: HD

PSG grouping: 01

Daily work schedule:DWRS

here i am getting customising error in work schedule rule 2 HD 01 DWRS

can some please help me out in solving this problem.

Thanks,

Sreekanth

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

Thanku Experts..

problem solved

Former Member
0 Kudos

Pls. Check PA-PSA and EG-ESG grouping.

Possibly you may have missed any grouping value.

Regards

Ajay

Edited by: Ajay3326 on Feb 10, 2012 10:37 AM

Former Member
0 Kudos

Hi,

Please check WHETHER have you assigned holiday calander properly and pws in table V_T508A and also all grouping ES and PS Grouping.

Thanks

sikindar_a
Active Contributor
0 Kudos

Check the Groupings and dates