on 02-10-2012 8:09 AM
Dear Experts,
i have created holiday calendar (HD), personal subarea grouping 01, daily work schedule as NORD, defined period work schedule as GENL(general Shift), i have taken 2(salaried staff) as work schedule grouping, work schedule rule as DWSR.
when i am doing generate work schedules manually i am giving
ESG: 2
Hoilday caleder: HD
PSG grouping: 01
Daily work schedule:DWRS
here i am getting customising error in work schedule rule 2 HD 01 DWRS
can some please help me out in solving this problem.
Thanks,
Sreekanth
Thanku Experts..
problem solved
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Pls. Check PA-PSA and EG-ESG grouping.
Possibly you may have missed any grouping value.
Regards
Ajay
Edited by: Ajay3326 on Feb 10, 2012 10:37 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please check WHETHER have you assigned holiday calander properly and pws in table V_T508A and also all grouping ES and PS Grouping.
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Check the Groupings and dates
in table T508A..and grouping table V__001P_ALL and V_503_ALL
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.