cancel
Showing results for 
Search instead for 
Did you mean: 

Do you require SPM when implementing CLM Wave 7. OP

Former Member
0 Kudos

I am implementing CLM with ERP integration Wave 7 OnPremise solution

1.Do I have to implement SPM to roll out CLM? I know that CLM comes with its own reports, do they require SPM to work?

2. We have Contract Managment Reports and Spend And Compliance reports.in CLM ...do they work without implemention SPM

cheers

alex

Accepted Solutions (1)

Accepted Solutions (1)

0 Kudos

Hi Alex,

SPM is not a requirement for implementing CLM. CLM reports are standalone driven by the CLM query framework and it does not require SPM. SAP recommends using SPM for Spend and Compliance.

Hope this clarifies.

Regards,

Vikram

Answers (0)