on 02-09-2012 8:59 AM
Hello,
We have implement GATP in our businness and we are facing a problem concerning scheduling.
For example: we increase the hours dedicated to transport operations in scheduling. After BOP there is no change in material availability date (although in BOP_RESULT I can see that the change in conditions is applied). That means that BOP do not send any change to ECC i.e. no rescheduling of dates is done, which I think is wrong.
Is this a normal situation?
I have already checked the "Rescheduling" switch in BOP
Best Regards
Pablo
HI Pablo,
You need to reset the scheduling buffer when doing a change on the customizing. Run report /SAPAPO/SCHED_BUFFER_RESET and enter the corresponding locations. The buffer is resetted automatically after a certain timeperiod (I think 30mins), so the system is using still the old values for scheduling if you just changed the customizing.
best regards,
Michael
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.