on 02-09-2012 8:37 AM
Dear experts,
The Present configuration allows GR date prior to PO creation date. The system allows users to post Goods receipt (MIGO), even if the GR date is prior to the PO creation date.
How to restrict this? Is there a standard customization in MM or it requires ABAP programming?
Please suggest me a solution as early as possible.
Thanks in advance.
Sathyaraj
Edited by: Jürgen L. on Feb 9, 2012 5:33 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sathyaraj,
Could you please check once whether 'Delivery completed indicator' has been selected in po,if it is so ,system allows GR in advance.Or else as per best of my knowledge is concern it could be the cause of in the t-code omcq 00 M7 made it as a warning.
Sridhar G
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Set this message as error in customizing in OMCQ
And set 00 M7 - 254 message as error message so that user cant receive material before delivery schedule date
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI
requierd ABAp prograamming for same you have to use exit
table will be EKKO help for PO creation date
Logic will be while saving MIGO system will compare PO creation date from table EKKO and Posting date of MIGO
Regards
Kailas Ugale
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
there are lot many User Exits /BADI available for goods receipt make use of it
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.