on 02-09-2012 7:00 AM
Hi Guys,
I want to activate WCM in the PM order when i enter WCM control key in operations.
I do NOT want to activate it using "Activate Work Clearance Management for Maintenance Orders".
I have done all the config but maybe i missed something as the work approval icon is not appearing for WCM key in order.
Can someone think of what i may have missed?
Hi,
Please check whether you have marked the setting :-
Plant Maintenance and Customer Service ->Work Clearance ManagementMaster data -Maintain Application Profile ->Here check whether you have marked WCM Operations field ..
Thus after doing all other settings,
Using WCM Control Key - u should be getting
Here if you would be getting WCM Operation additional icon in taskbar ...
regards
giri
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.