Dear Experts,
The Plant maintenance user is expecting the PM orders to be settled automatically without manual interaction i.e with out executing K088 or KO8G.
Is it possible to met their requirement. If yes please provide the solution in detail. Is there any change in the configuration required?
Jyoshna
Schedule run of KO8G on a particular date as background job with the help of your Basis consultant.
However it is not advisable as errors if any existing will go undetected.