on 02-08-2012 6:59 PM
Hi all,
Is it possible to consider the special stock (table MSLB) when I run MRP (MD01)?
The type os special stock is 'O'
Thank in advance,
Felipe Simionatto
Edited by: fsimionatto on Feb 8, 2012 8:09 PM
For special stock O please you may wanna look at the note 743312
Also the thread for more info
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Special stock cannot be included in the MRP run, either you have to make it unrestricted or implement a BAdI or userexit.
BAdI/Enhancement implementation may not be very reliable :
The following BAdi's are available for MRP related stuff
MD_ADD_COL_EZPS BAdI: Extra Columns for Evaluation PP-MRP Reqmnts P
MD_ADD_COL_OVERVIEW BAdI: Display of Additional Columns in the Material
MD_ADD_ELEMENTS
MD_ADD_ELEMENTS BAdI for Adding Additional Requirements/Receipts
MD_CHANGE_CALENDAR BAdI: Change Calendar for Range of Coverage Calcula
MD_CHANGE_MRP_DATA BAdI: Change Data when Importing MDPSX
MD_DISPLAY_ELEMENT BAdI for Changing Display of MRP Elements
MD_DISPLAY_ELEMENT
MD_EXPORT_TREE Order Report: Export Contents of the Order Tree
MD_EXT_SUP BAdI for Determining the Issuing Storage Location
MD_INTERACT_PLANNING BAdI for Deactivating Changeability of MRP Elements
MD_LAST_LOT_EXACT BAdI for Calculating Last Lot Exactly in Individual
MD_M61R_DELKZ_POPUP Definition: Display data for MRP element (MD04)
MD_M61R_EXT_REQS_TXT Definition: Supplement data of MRP element for ext.
MD_M61X_EXT_REQS_GET Definition of selection of external rqmts in FuGr M
MD_MODIFY_PRODVERS BAdI for Modifying Production Version
MD_MODIFY_SOURCE BAdI for Modifying Source Determination in MRP
MD_MRP_LIST BADI for further processing of MRP list
MD_MRP_PARAMETERS BAdI: Change Planning Parameters
MD_MRP_RUN_PARALLEL Add-Ins for parallel planning run of requirements p
MD_PIR_FLEX_CONS BAdI for flexible planned ind. req. consumption/red
MD_PLANNING_RESULT BADI for Issuing Planning Result
MD_PLANNING_SCENARIO BAdI for Maintenance of Add. Parameters in Planning
MD_PLDORD_BOMEX_CIF BAdI: Deactivation of BOM Forced Explosion in CIF
MD_PLDORD_CHANGE BAdI for Changing Planned Orders
MD_PLDORD_POST BAdI: Update of Planned Orders
MD_PLDORD_SCHEDULING BAdI: Schedule Planned Orders
MD_PLDORD_TIME_STAMP BADI for publishing time stamp problems
MD_PURREQ_CHANGE BADI for changing purchase requisitions
MD_PURREQ_POST BADI for updating purchase requisitions
MD_PURREQ_REL_STRAT BAdI for Deactivating Release Strategy for MRP Purc
MD_STOCK_TRANSFER BADI: Change the Requirement Date During Stock Tran
MD_SUBCONT_LOGIC BADI: Determine Subcontracting Logic
Available userexits for MD01.
LMDR2001 User exits restr. profiles of opt. pur.ord.-based load bldg
LMDZU001 User exits in additional planning
Edited by: Jeevan Sagar on Feb 8, 2012 2:30 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.