Hi,

In import Scenario, i have made imports duties as an item level condition. Suppose i have 10 material in a PO and 7 duty components. When i do Customs MIRO it shows 70 line items. It becomes very tidious process to fill all the line items manually. Can we enter only 7 line items applicable for all the 10 items in MIRO.

Regards,

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

In MIRO system proposed all the line items and you have to just enter the header details. what are you entering at item level and its difficult?

Former Member
0 Kudos

Is this is not possible in standard SAP

Former Member
0 Kudos

Hi!

please try BAdI MRM_UDC_DISTRIBUTE

method amounts_calculate

or BAdI MRM_INVOICE_SPOT

enahncement ES_BADI_INVOICE_UPDATE

method process_at_save

I hope this will help

Florian

brinda_r
Active Contributor
0 Kudos

Hi,

That is not possible

Regards

Brinda

Former Member
0 Kudos

Can you suggest some work around.