on 02-08-2012 8:19 AM
Hi,
I have settting up refurbishment order. will the costing variant would be different for ref.order from normal maintenance order?
Please advise!
Regards,
Meghana
hi
Costing variants are assigned at order type level.Discuss with your FICO team assign accordingly.
you can assign same costing variants to all order types as per your business requirements.
Settlement profile will be different from breakdown or preventive orders.refurbishment orders are settled to Material
Regards
Seenu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Costing variants contain control parameters for all aspects of costing.
The costing variant forms the link between the application and
Customizing, since cost estimates are created and saved with reference
to a costing variant.
The costing variant controls how costing is executed, such as:
o Whether the costing results are planned costs or actual costs
o Which prices are used to valuate materials, internal activities, and
external activities
o How overhead is calculated
A costing variant includes the following groups of settings:
o Costing type
o Valuation variant
o Number range assignment
to know more about Costing part , dicuss with your CO consultant,
try OIOF tocheck for the costing variant assigned to Refurbishment order type. Remember Refurbishment order will be settled to the Material itself not to the Cost Center
Regards
Prakash
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.