What are the Master Data Elements and Config Elements that needs to be considered in the Scheduling Agreement.What are the mandatory fields that are to be maintained in it.Please let me know.
Thanks in Advance
Regards
Krisjohn
this is a very generic question as SA in procurement has many functions and need various config settings to achieve these functions, so would advise to have a look at first thread of this forum to read about SA and then post specific question related to topic not understood.
you would like to read about following points about SA (these are few important ones but there are many other aspects also):
SA creation and release
SA delivery schedule lines
SA in planning (MRP)
SA release
processing deliveries against SA (SA with delivery orders)
validity periods in SA
JIT / forecast delivery schedule
yogesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Material master - activate JIT indicator in purchasing view, its useful to determine the JIT schedules
Create Creation profile - Tcode OMUP - its useful define JIT and forecast period and whether backlog is allowed
Vendor master - Assign creation profile in vendor master(additional data) or directly in scheduling agreement.
Source list - If you create automatic schedules using MRP, you need to assign MRP relevant indicator and enter the scheduling agreement in source list.
Output schedules - Create condition record with MN10 if you want to print or mail the delivery schedules
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.