Fetching the latest drawing No. after changing Sampling Drawing Procedure

Hi QM Masters,

I have 1 Report in that I fetch Drawing No. against Inspection Lot.

When I create a Inspection Lot at that time Drawing No. will generated in the system. Sampling Drawing procedure is assigned to the Lot. But the problem is that When I change the sampling procedure New Drawing No. is generated against the same lot.

Both Drawing No. are updated in QPRS table against the same lot. That's why It is difficult to fetch the latest Drawing no.

How I fetch the latest drawing no. after changing the SDP?

Gives me the Expert logic to fetch the data.

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Feb 07, 2012 at 11:01 AM

    Hi can you check the fields ENTDATUM and ENTZEIT for sample drawing date and time or this date is different for you in the same table QPRS

    Regrads,

    Smruti

    Edited by: smruti.ranjan on Feb 7, 2012 12:02 PM

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.