on 02-06-2012 12:17 PM
Dear Experts,
One of our customer wants to post landed cost for the partial quantity in a GRPO. In landed cost, quantity column is greyed out and if copy from a GRPO it is showing all the quantity.
Is there any other option to post landed costing for partial quantity in a GRPO.
Pl help.
Thks and rgds
Sundaram
Hello Sundaram
Have you been able to solve it??
Thanks
Jacobo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sundaram........
This is SAP standard Functionality that SAP makes Landed cost for Full Qty by default. You can not make it for Partial.......
Regards,
Rahul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.