Forecast consumption by Distribution demand planned (Preqrel)

Hi Experts,

I have a requirement where in forecast should get consumed by Distribution demand planned (Preqrel) .

I have maintained the following settings.

1).Added category BH to category group Z01 and assigned the category group to requirement strategy 20 in APO.

2).Assigned this strategy 20 to product masters in APO with backward/forward consumption.

But when i run heuristics, the forecast at source location doesnot consumed by Distribution demand planned (Preqrel) .

Can you please help if i have missed any setting OR if there is any other solution to meet this requirement?

Thanks in advance

Regards

Binil

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on Feb 07, 2012 at 12:36 PM

    Hi Binil,

    Heuristics doesn't lead to consumption of a demand element. It only plans for the net requirements.

    Consumption happens only for Sales Order, where Sales Order will consume the forecast during the CIF itself.

    If you want that AFTER your Heuristics run, the forecast should get reduced by the amount of the distribution demand planned, then you could write a macro that could do this kind of calculation. Use this macro in a DP activity which would be used in a DP background job that could run after your Heuristics.

    Please note that this won't be actually consumption. Your total demand will include the distribution demands (planned/confirmed, etc) and would also include the forecast.

    If you want to delete the forecast based on the Distribution Demand planned BEFORE you run the Heuristics, then you could run the above macro in a background job before you run the Heuristics. Please note that this would be actual deletion of the forecast, and then this "deleted" forecast would no longer be a part of the total demand.

    Hope this helps.

    Thanks - Pawan.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.