on 02-03-2012 4:46 AM
Hi Gurus,
1. Resource availability-As per business requirement while creating/releasing the order system should propose the resource (Work centre) availability
Pls let me know if any standard setting is there or we have to go for user exit.
Hi,
I am not sure of resource availbility but you can check capacity availability check while releasing the work order ,
You can do by assigning an Overall Profile to combination of Plant & Order type in OIOI for business function 2
You can remove tick mark in No Check option for Capacity availability & for release order give option as 3
At the same time at work center for Capacity header you should have to Relevant to Finite Scheduling marked ..
Thus once u have all the above settings when u release the Order system performs capacity avaibility check at work center and suggests a new date when capapcity is available ..
regards
giri
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Fried,
As per your instruction i maintained the overall profile SAPSFCG013,release order-3 and removed no check tick also set the finite scheduling indicator in work centre.but still it is not checking the avalabilty for example i created/released the order A of work centre W of 1 resource per day 8 hrs and for the same scheduling time the work centreallowed me to create another order B.so pls let me know what i need to check further???
Hi now i have used overallprofile SAPPM_G013 then working fine..nice suggestion...
Edited by: Bkumar123 on Feb 3, 2012 1:00 PM
User | Count |
---|---|
91 | |
7 | |
7 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.