Hi Gurus,

1. Resource availability-As per business requirement while creating/releasing the order system should propose the resource (Work centre) availability

Pls let me know if any standard setting is there or we have to go for user exit.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

I am not sure of resource availbility but you can check capacity availability check while releasing the work order ,

You can do by assigning an Overall Profile to combination of Plant & Order type in OIOI for business function 2

You can remove tick mark in No Check option for Capacity availability & for release order give option as 3

At the same time at work center for Capacity header you should have to Relevant to Finite Scheduling marked ..

Thus once u have all the above settings when u release the Order system performs capacity avaibility check at work center and suggests a new date when capapcity is available ..

regards

giri

Former Member
0 Kudos

Hi Fried,

As per your instruction i maintained the overall profile SAPSFCG013,release order-3 and removed no check tick also set the finite scheduling indicator in work centre.but still it is not checking the avalabilty for example i created/released the order A of work centre W of 1 resource per day 8 hrs and for the same scheduling time the work centreallowed me to create another order B.so pls let me know what i need to check further???

Hi now i have used overallprofile SAPPM_G013 then working fine..nice suggestion...

Edited by: Bkumar123 on Feb 3, 2012 1:00 PM

ajitkumar
Active Contributor
0 Kudos

pl check how capacity is maintained in the work center.

if in the planning details, it is enabled for several operations , assigning to 2 operations are possible