Stock stransfer requisitions for few products are not visible in Interactive TLB view. The only difference in master data for such products is planned delivery time 0. If I change the transport duration in transportation lane from 240:00 to 0 hours, then these stock transfer requisitions becomes visible in Interactive TLB view. Please advise.

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Posted on Feb 01, 2012 at 12:19 PM

    Hi,

    When you select the specific T- Lane in TLB view, click on "TLB params" button and see the dates appearing in the section "data selection period".

    May be, once you maintain the transportation duration as 240:00, the stock transfer's dates are going out of the date range.

    So, it no longer remains relevant for TLB.

    Thanks - Pawan

    Edited by: Pawan Pathak on Feb 1, 2012 1:19 PM

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Feb 02, 2012 at 04:46 AM

    Hi Pawan,

    Thanks for reply. I checked as per your suggestion, but transfer dates are not going out of the date range. There are two orders for two products with the same demand date, availability date & transport duration 240:00 hours but the only product is visible in Interactive TLB view which is having 'planned Delivery Time' maintained. For these two products no 'GR Processng Time' & 'GI Processng Time' are maintained at destination location.

    Could you please explain the relationship between data loading in TLB view & order transit time (planned del. time & transport duration)

    Regards,

    Add a comment
    10|10000 characters needed characters exceeded

    • Hi Pawan,

      Planned delivery time referred here is maintained in product master (Not one in T-Lane).

      Both products are in same T-Lane, i.e. source location, destination location & transport duration are same.

      Planning calendar is 24X7.

      Dates in data selection period are todayu2019s date & today+365 date (i.e. 07.02.2012 & 06.02.2013)

      I checked as per our suggestion; demand date is not less that start date in TLB profile.

      I tested different scenarios by maintaining planned delivery time in product master & Transport duration in T-Lane, the summary is as per below.

      PDT = 0, Transport duration = 0:00, TLB view = OK (Orders visible)

      PDT = 0, Transport duration = 240:00, TLB view = Not OK (Orders visible)

      PDT = 1, Transport duration = 0:00, TLB view = OK (Orders visible)

      PDT = 1, Transport duration = 240:00, TLB view = OK (Orders visible)

      PDT = 10, Transport duration = 0:00, TLB view = OK (Orders visible)

      PDT = 10, Transport duration = 240:00, TLB view = OK (Orders visible)

      Orders are not visible only in case, where PDT in product master =0 and T-lane transport duration >0.

      Thanks & Regards,

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.