Hi there,

I added a dual-stack SAP system (Netweaver 7.0 BI) to my Solution Manager, latest release und patches.

I used the managed system configuration wizard to add it.

Everything is green ... bit I'm still not able to use the Maintenance Optimizer.

In step 2 I'm getting the error message "System constellation is empty, calculation will not run".

No Notes, no further information.

What could be the cause of this?

Thank you!

System constellation is empty, calculation will not run
Message no.MOPZ_MSG_DELTA_CALC001

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

4 Answers

  • Jan 27, 2012 at 11:39 AM

    Hi,

    I got this sap note [Note 1630517 - MOpz: fix "System constellation is empty" in manual mode|https://websmp130.sap-ag.de/sap(bD1lbiZjPTAwMQ==)/bc/bsp/spn/sapnotes/index2.htm?numm=1630517]

    before that I would like to tell please make sure you have properly assigned relevant product instance and assigned product version and applied latest MOpz correction notes.

    please update

    Thanks,

    Jansi

    Add comment
    10|10000 characters needed characters exceeded

  • Jan 27, 2012 at 02:18 PM

    Hello there,

    Usually this is due to java product instances without Java technical system assignment.

    Please check http://help.sap.com/ -> SAP Solution Manager 7.0 -> SAP Solution Manager7.0 EHP1 SP23 (English) -> Basic Settings -> Solution Manager system landscape -> the parts about Java technical system assignment, automatic data capture... might help.

    Best regards,

    Miguel Ariñ

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jul 25, 2012 at 12:00 PM

    Hello,

    i facd same issue while doing the MOPZ for solman upgrade.

    i solved the issue by checking the smsy setting for solman java part. in header data tab i found planned and production check box were not selected , so i selcted production and save the changes.

    restart the MOPZ issue reolved.

    regard,

    SH

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hello All,

      I faced a similar issue as well & solution provided by Sherif worked for me.

      Best Regards

      SB

  • avatar image
    Former Member
    Nov 27, 2012 at 03:25 PM

    Hi,

    for ABAP systems, please check is there any product assigned in Header data tab in SMSY.

    Laszlo

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hello all,

      Please execute SAP_LMDB_LDB_0000000001 and LANDSCAPE FETCH job then reexecute the MOpZ transaction again

      I have the same issue has found the solution with above steps