Hi,

The n/w is released also activity is released but the material component assigned are still in created status. PR,PO and GR for the material done but GI not allowed because of this status movement allowed is untick.

Please suggest.

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Jan 27, 2012 at 06:08 AM

    hi

    check whether you have the status in the material master and change it to the required status in MM02 and proceed.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Feb 02, 2012 at 06:55 AM

    Hi,

    Please check for OSS notes - I have seen this issue earlier, there are some notes.

    Regards

    Shrikant

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.