Stock in bonded warehouse to consider in MRP

64 Views

We are bonding some of imported consignment in custom bonded warehouse. It is being ex-bonded whenever it is required in factory unit for consumption.

When we run MRP , system recognises only stock maintained in factory. We want stock maintained in bonded warehouse to consider in MRP run. This will give us proper clarity & will throw requireemnt only when it is required after considering stock at factory as well as stock in warehouse

Can we have resolution for the same

regards